Given is a PERT project network diagram as shown below a The

Given is a PERT project network diagram as shown below. a) The Project Completion time = (in 2 decimal places) b) The Earliest Start time, ES, of Activity G = (in 2 decimal places) c) The Latest Finish time, LF, of Activity C = (in 2 decimal places) d) The critical activities are = ________ (ex. Type in critical activities as ABCD, no comma, no space)

Solution

The project can be completed in the order given in the Pert diagram.

If we start there are different paths as follows:

1) A C F H -- Time taken = 1.52+7.02+4.36+3.25 = 16.15

2) A C E G H--Time taken = 1.52+7.02+1.28+6.24+3.25 = 19.31

3) B D G H --Time taken = 2.36+3.69+6.24+3.25=15.54

Earliest time for completion of project = 15.54

Maximum time for completion of full project = 19.31

b) Earliest time for activity G = Earliest of( ACE , BD)

= BD = 6.05

c) The latest finish time for activity C = 1.52+7.02

= 8.54

d) The critical activities are (ACEG, BDG) and (ACFH, ACEGH, BDGH)

 Given is a PERT project network diagram as shown below. a) The Project Completion time = (in 2 decimal places) b) The Earliest Start time, ES, of Activity G =