2 The Forging Department accepted Job 507 on May 15th to mak
2· The Forging Department accepted Job 507 on May 15th to make 1,000 widgets. To complete the job they requisitioned 1,100 sheets at $3.25 per sheet and 1,150 grommets at $0.44 per set. The cost driver that the Forging Department uses is drop-forge strokes which are counted on a machine mounted counter. $3.75 is applied as overhead for each drop-forge stroke. Additionally $600.00 of overhead is applied to each job due to setup and teardown. Direct labor is applied at $28.00 per hour for the machine operator and $19.00 for the machine loader. The job required 17 hours of labor by the team. When the job was complete Job 507 was transferred to Finished Goods Inventory (FGID. When the job was transferred, 45 sheets were returned unused to raw material inventory, 85 grommet sets were returned, and there were 2,115 strokes on the counter. Journalize all events depicted as of May 15th.
Solution
Sr. No Particular Debit Amount Credit Amount 1 Sheet A/c Dr $ 3575 To Job 507 $ 3575 2 Gromments A/c Dr $ 506 To Job 507 $ 506 3 Machine Overhead A/c Dr $ 3.75 To Job 507 $ 3.75 4 Overhead A/c Dr $600 To Job 507 $ 600 5 Direct Lobour A/c Dr $ 476 ` To Job 507 $ 476 6 Machine Loader A/c $ 19 To Job 507 $ 19 7 Job 507 A/c $ 149.99 To Sheet $146.25 To Gromenet $ 3.74 8 Job 507 A/c $ 5029.76 To Finish Googs $5029.76