In linear scheduling, if the second activity has a much higher rate than the first one, then we apply the distance (or time) buffer to the end of the activities.

True

False

Solution

yes. True.

If horizontal distance is higher, we apply time buffer

and if vertical distance is higher, we apply distance buffer.

In linear scheduling, if the second activity has a much higher rate than the first one, then we apply the distance (or time) buffer to the end of the activities