     Grades to Homework chapter 2 Help Save & Exit Submit Check my Exercise 2-9 Job-Order Costing and Decision Making [LO2-1, LO2-2, LO2-3 Taveras Corporation is curenty operating at 50% of its avalable manufacturing capacity. uses a joborder costing system with a plantwide predebermined overhead rate based on machine-hours. At the beginning of the yeat the company made the folowing 20 Machine-houre required to support estinated predaet ion 5,720,000 Required: t. Compuie the plantwide peedetermined overhead rate. 2. During the year, Job P90 was started, completed, and sold to the customer for $4,400. The following information was available with eespect to this job Compute the total manufacturing cost assigned to Job P90. Complete this question by entering your answers in the tabs below  5 7 8 9     
 
  
  Solution
1. Plantwide overhead rate :
Fixed overhead rate = 5720000/260000 = 22 per machine hour
Total overhead rate = 22+2 = 24 per machine hour
2. Calculate total manufacturing cost assigned :
| Direct material cost | 2024 | 
| Direct labour cost | 1452 | 
| Overhead cost (91*24) | 2184 | 
| Total manufacturing cost | 5660 | 