Compute the NPV for Project M if the appropriate cost of cap
Compute the NPV for Project M if the appropriate cost of capital is 7 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.)
| Compute the NPV for Project M if the appropriate cost of capital is 7 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) |
Solution
Solution: NPV $519.90 Project should be : Accepted Working Notes: a b c= a x b Year Cash Flow PVF @ 7% Present value 0 -2,000 1 -2,000.00 d 1 550 0.93457944 514.01869 e 2 680 0.87343873 593.93834 f 3 720 0.81629788 587.73447 g 4 800 0.76289521 610.31617 h 5 300 0.71298618 213.89585 i NPV 519.90 j= NPV = d+e+f+g+h+i The project M should be accepted as NPV is positive $519.90 Notes: PVF is calculated @ 7% = 1/(1+0.07)^n where n is the year of cash flows for which PVF is calculated. Please feel free to ask if anything about above solution in comment section of the question.