The load profile shown in Table A must be supplied using the
Solution
None of the solutions provided table C are feasible. Here are the reasons: Let us consider solution 1 ( S1 ). In this solution, the MW of power provided in hour 1 is 350 ( 100 MW + 250MW ) only, while the requirement is
400MW. Now, in case of solution 2 ( S2), although by addign each of the MW in each hour, we are getting the required MW as mentioned in table A ( i.e, 150+250=400 which is same as the hour 1 requirement of table A, 250+250=500MW which is same as the requirement of hour 2 of table A, 100+250+250=600MW which is same as the requirement of hour 3 of table A, 200+200=400 which is same as the requirement of hour 4 of table A ), but C cannot be up for more than 3 hours at a stretech. However the table is indicating C is running for all the 4 hours. Hence this solution is also not feasible,\'
Now consider solution S3. In this case, the power drawn from unit B is 40 in hour 3 which is less than its minimum capacity. Again, power drawn from unit C in hour 3 is less than its minimum capacity which 150MW. Hence this solution is also not feasible.
Since none of the mentioned solutions are feasible, it is not possible to calculate the cost.

