6 7 9 5 Given an activitys optimistic most likely and pessim

       6
       7
       9
       5

Given an activity\'s optimistic, most likely, and pessimistic time estimates of 2, 5, and 14 days respectively, compute the PERT expected activity time for this activity. (Points : 1)

Solution

Given that,

optimistic (O) = 2

most likely (M) = 5

pessimistic (P) = 14

The PERT expected activity time for this activity is,

(P+ 4M + O)/6

(14 + 4*5 + 2) / 6 = 6

First option is correct.

 6 7 9 5 Given an activity\'s optimistic, most likely, and pessimistic time estimates of 2, 5, and 14 days respectively, compute the PERT expected activity time

Get Help Now

Submit a Take Down Notice

Tutor
Tutor: Dr Jack
Most rated tutor on our site