265 A new product made from recycled bioplastics G needs 20

2-65 A new product made from recycled bio-plastics G needs 20 labor hours to complete the build for the first unit. If production operates at a 85% learning curve rate, calculate the average labor hours required per unit to produce five units

Solution

The learning curve formula is

T5 = Axb where

T5 = Total time rquired to produce 5 units

A = Average Time or labour hours required to produce first unit = 20 hours

x = unit number & b = constant which is calculated as logP/ Log2 where P = learning percentage = 85% in this case

Here b = log.85/log2 = -0.234

Therefore average labour hours required to produce 5 units is

T5 = 20 (5-0.234 ) = 13.72 hours