What would the allocated cost for all overhead costs for job
What would the allocated cost for all overhead costs for job 607 be
Gwynnie Pie Company makes dessert pies for national fast food chains. Gwynnie Pie Company is considering using ABC costing and has the following activity cost pools and information available Activities Material handling measured by $252,000 batches Mixing measured by batches $111,000 Packaging measured by units $86,000 Maintenance measured by # of $15,000 setups Estimated Overhead Costs Estimated Activity 2,400 batches 2,950 batches 2,150,000 units 260 setupsSolution
Total O/H for Job #607 :-
Material Handling (252000/2400 batches) * 5 batches
525
Mixing (111000/2960 batches) * 5 batches
187.5
Packaging (86000/2150000 units) * 5500 units
220
Maintainance (15000/260 setups) * 1 setup
57.69
Total O/H for Job #607
990.19
*No of Baches required for Job #607 = 5500/100 = 5 batches
Option C is correct
| Material Handling (252000/2400 batches) * 5 batches | 525 |
| Mixing (111000/2960 batches) * 5 batches | 187.5 |
| Packaging (86000/2150000 units) * 5500 units | 220 |
| Maintainance (15000/260 setups) * 1 setup | 57.69 |
| Total O/H for Job #607 | 990.19 |